How much concrete for a 20 ft wall?
A 20 ft long × 8 ft high × 8 in thick wall needs 106.7 cubic feet, or 3.95 cubic yards, before waste. Add 10% for about 4.35 cubic yards.
Wall calculator
Estimate the concrete needed for a poured wall, stem wall or retaining wall. Enter the wall length, height and thickness to get volume, bags, rebar and cost.
Last updated:
Wall volume = length × height × thickness. Convert the thickness from inches to feet by dividing by 12, then divide the cubic feet by 27 for cubic yards.
20 × 8 × (8 ÷ 12) = 106.7 cubic feet. Divide by 27 to get 3.95 cubic yards. Add 10% waste for about 4.35 cubic yards, or roughly 204 × 80 lb bags. Ready-mix is usually the practical choice at this size.
| Size | Concrete | 80 lb bags* |
|---|---|---|
| 10 ft × 4 ft × 6 in | 0.74 cu yd | 35 |
| 20 ft × 4 ft × 6 in | 1.48 cu yd | 70 |
| 20 ft × 8 ft × 8 in | 3.95 cu yd | 185 |
| 30 ft × 6 ft × 8 in | 4.44 cu yd | 208 |
*Before waste. Add 5–10% for spillage and uneven subgrade.
A 20 ft long × 8 ft high × 8 in thick wall needs 106.7 cubic feet, or 3.95 cubic yards, before waste. Add 10% for about 4.35 cubic yards.
Residential stem walls are often 6–8 in thick. Retaining walls and load-bearing walls need an engineered thickness based on height, soil and loads. Do not size a structural wall by rule of thumb alone.
A 20 ft × 8 ft × 8 in wall needs about 185 × 80 lb bags before waste, or roughly 204 bags with 10% waste. At that scale, ready-mix is usually cheaper and faster.
Most structural and retaining walls use horizontal and vertical rebar. The size, spacing and cover depend on the design; follow the engineered plan or local code.
Use the wall length, height and thickness in the calculator. Retaining walls also need a footing, drainage and an engineered design; the concrete volume is only one part of the estimate.
At $120–$180 per cubic yard, 4.35 cubic yards of ready-mix costs about $520–$780 before delivery. Formwork, reinforcement, excavation and finishing are separate costs.